closed

Chamilo 1.8.8 beta packaging

Added by Yannick Warnier over 12 years ago. Updated over 12 years ago.

Status:
Feature implemented
Priority:
Normal
Category:
-
Target version:
Start date:
12/02/2011
Due date:
14/02/2011
% Done:

100%

Estimated time:
8:00 h
Spent time:
Complexity:
Normal
SCRUM pts - complexity:
8

Description

Time related to all tasks around the packaging of 1.8.8 beta should be logged here.

Actions #1

Updated by Yannick Warnier over 12 years ago

OK, we've closed all bugs scheduled for 1.8.8 beta. Now starting package, then we'll be on the road for an RC or maybe directly the stable.

Actions #2

Updated by Yannick Warnier over 12 years ago

  • Status changed from Assigned to Feature implemented
  • % Done changed from 0 to 100

Package uploaded to google code